Brune and Bernard House – Lift Project
Delivering on the final part of our promise, we have now commissioned architects, surveyors and engineers to design, procure and deliver new lifts for Brune House and Bernard House. The works will involve the construction of external lift shafts, alongside the redesign and relocation of refuse and bin stores.
Our architects are in process of design and engagement with Tower Hamlets Council's planning department. Residents were consulted during the design process and you can view planning documents below.
Building works will be undertaken in phases to ensure safety and manage and minimise the disruption to residents.
- Value: £4million
- Timescale: Anticipated Start: 2027; Completion 2030
- Surveyors, Architects & Engineers: Ingleton Wood
- Contractor: To be procured.
- East End Homes Project Manager: Wayne McAllister